DADANCODADANCO
NewsContactPress RoomJobsCompany ProfileProductsApplicationsProjectsFAQHome

  FAQ
  Comparing Dadanco
& other Systems
  Energy Related Issues
    System Design
  Unit Performance
  Piping & Insulation
  Heating
  Testing, Commissioning
& Maintenance

 


Providing true comfort air conditioning

  System Design

Can the existing duct and SCHW systems be reused in a retrofit project with Dadanco units replacing the original induction units?
 Yes. The primary air flow will be the basis of the new selection for the Dadanco units. This means the duct velocities will remain the same, and hence the duct static pressure losses. The overall system static will reduce when the changeover is complete and no old units are operational and require the original higher pressure at their locations.
 
The secondary water flow will remain the same, although there have been proposals to increase it by 10% to cater for increased room loads. This decision is for the designer when deciding if the increase in pump power is acceptable in the overall energy equation. With the range of coils available in the Dadanco units and the secondary air flows achieved with the new nozzles, this usually means a significant improvement in total unit capacity, with the original fluid flows and infrastructure.
 

Can the one primary air AHU feed all of the perimeter induction terminal units for a floor?
 Yes. The correct selection of the primary air flow and temperature makes this possible. The disadvantages to the scheme are physical ones relating duct size, ceiling space, riser locations and the internal zone ducts and boxes. However, if the building has large areas of glazing on the North face (southern hemisphere applications), which results in the peak cooling load for this face occurring in mid-winter, it may be better to have a separate AHU for the northern zone.
 
What is the effect of the fan motor heat on the primary air in a draw-through AHU?
 The effect is to raise the temperature of the air leaving the air handler. The change can be represented on a psychrometric chart as a sensible heat increase, with the air leaving condition shifted to the right by whatever is the calculated rise in dry bulb temperature. This rise needs to be factored into the system design, as the primary air condition at the primary air plenum of the units must still be that used in the selection process.
 
How is condensation controlled in high humidity environments?
Outdoor air is pre-conditioned and dehumidified in the primary air AHU, along with any return air needed to make up the primary air total. The building is maintained at a slight positive pressure with respect to the outside to control infiltration of humid air. Once the dehumidified air is supplied to the space, the air dew point is monitored as well as the secondary water temperature, the control system using this data in the control strategy to provide conditions where condensation will occur.
 
There are a range of strategies that can be employed to suit any particular project. These include re-setting the SCHW water temperature up; switching the SCHW pump off for a period; overriding the primary air temperature control to increase the rate of dehumidification at the primary air cooling coil; at start-up after a weekend, operation with primary air only until the space humidity is reduced to unacceptable level, and more. Refer to the Controls section of the Dadanco System handbook.

 
What about the system shutting down at night? Won’t the humid air infiltrate and cause a condensation problem at start up?
The system can and should be shut down at night to save energy. This will probably lead to some infiltration of humid air, and the humidity in the space will increase. In Singapore for example, our experience indicates that the space humidity increase by as much as 10 – 15% over a weekend shut down. However, when the system is started up on Monday morning, the controls always calculate the dew point and maintain the secondary water temperature slightly above the dew point. During normal operations, this differential is always maintained with good controls.
 
This control of the secondary water can be incorporated with the optimum start program, to achieve savings over a conventional system. During start up with a conventional system, the air handlers are typically started and the chilled water valve goes wide open to provide maximum flow to the cooling coil.
 
With optimum start the first operation of the cooled and dehumidified air is to flush the moisture out of the space. This is referred to in 4.4 above.

 
Do you need to use high velocity duct in an induction sytem?
 No. With the pressure in the plenum of an induction terminal unit being 150 – 250Pa, and no longer 450Pa and much higher, the total pressure in the supply system – the primary air duct system – allows the use of low pressure and low velocity duct sizing and construction.
 
How do you maintain the secondary water temperature?
There are three methods that can be considered. Options 1 and 2 below are for systems where all of the cooling for the installation originates at one or more chilled water units, or chillers. The third envisages a separate chiller for the SCHW circuit and will require the use of an energy program for verification. Brief details are:
 

1.       By circulating primary chilled water through a plate heat exchanger with the secondary water passing through the other side. The secondary water pump circulates the full secondary water quantity through one side while a modulating valve controls the primary water flow to achieve the design secondary water temperature. A sensor in the outlet of the secondary water line controls the modulating valve.
 
2.       The use of a mixing valve that allows an amount of primary water into the suction side of the secondary water circulating pump. There needs to be a connection back into the primary water loop to return a quantity of water equal to that introduced to maintain the secondary water temperature. A sensor on the leaving side of the secondary water pump controls the mixing valve.
 
3.       The use of a separate chiller to provide SCHW at the design temperature for this water circuit. The design of such a plant could have a connection to the primary water circuit, which would include a mixing valve (as 2 above), with the necessary isolating valves, to act as a back-up to the SCHW chiller. Remember the limits on suction gas temperatures if the chiller includes semi-hermetic compressors for such a higher temperature water application.
 
Is the connection to the unit plenum always on the end?
 No. The air connection into the plenum can be made into the centre of the side of the plenum. This is recommended where there is limited space between the units. It often eliminates a 90o bend from the duct connection to the plenum, which will reduce the duct static pressure losses.
 

This is applicable to CM perimeter units, Active Chilled Beams and induction diffusers.

 
Can an induction system comply with the building regulations for smoke control with central plant installations?
 Yes. AS1668.1: 1998 nominates two methods for smoke control in buildings. These are purging and zone pressurisation, commonly referred to as sandwich pressurisation. Induction systems can perform in either design.
 
All central plant systems have fire dampers in the supply air ducts where they leave the riser and enter the floor, as well as a fire damper in the return air opening into the riser system. If they are not the motorised type capable of remote control, a separate motorised shut-off damper will be adjacent and in positions that do not compromise the operation of the fire dampers.
 
AS 1668.1 does not give a specific value for the supply or exhaust rates for either system Rather it describes the required method of operation to achieve the intended result of excluding smoke from all non-fire-affected compartments. It also deals with other possible building air handling systems such as car park exhaust, but this does not concern us here.
 
For the zone pressurisation option in a building with an induction system, the operation of the plant and dampers in the air systems is as the code. The fact that the total air moved is lower than for an all-air system is of no consequence. The induction system is capable of maintaining the minimum pressure difference of 20Pa between the fire and non-fire compartments. This pressure difference is tested with all doors closed to required exits. The maintenance of the pressure differential is a function of the exhaust rate from the fire floor and the pressurising air supply to the non-fire floors.
 
For the purging system, the requirement is for a balance between the supply of uncontaminated outdoor air and the smoke spill discharge rates.
 
For both smoke control methods the current design procedures will provide an installation complying with the regulations.
 
It is of interest to note that additional control strategies apply to VAV systems in AS1668.1. In the commentary in Appendix B for Section 5, Central Plant Systems, it is required that all boxes must fail open or be driven open in a fire emergency, to allow outdoor air to flow into the non-fire floors. This extends to the wiring of these controls in a fire rated power supply. There is an alternative, which is to provide a dedicated motorised bypass damper to allow the air into the non-fire floors. In a number of layouts this would place this inlet close to the return or exhaust point.
 
The major energy saving with induction systems is in fan power. What is the situation with pumping energy?
 There is an increase in total pump energy as a result of the secondary water system. The primary water flow to air handlers is reduced, and the primary water pump energy is reduced accordingly. However, while the total pump energy for induction systems, primary and secondary, is higher than an all-air system, it does not significantly reduce the energy savings achieved by the reduction in the fan power.
 
As with any exercise in comparing energy usage between competing systems, each installation must be looked at separately, and the savings of each assessed and considered against the other factors of cost, ongoing maintenance and ease of installation.

 
Can the fan power saving resulting from retrofitting with Dadanco products be calculated simply?
 Yes.  As the change is to an existing system, there is no change to fan type, ducts and other airside characteristics, for which the formula for fan total efficiency can be used. This is:
 
Total Efficiency % = qV x ptF
                                  10 PR
 
where qV  =  volume flow of air, m3/s
 
          ptF  =  fan total pressure, Pa
 
          PR  =  power absorbed by the fan, kW
 
The 10 is a constant in this formula. If the fan total pressures are the same, as is the fan efficiency, then the power absorbed by the fans is in the ratio of the two air flow rates.
 
The question can be answered best by giving an example fro
m a project.
 
Example
 The following is an example of how to calculate the reduction in fan power when Dadanco units replace old units that operated on higher plenum pressures.
 
Given: The induction units in an existing system required 380Pa (1.5”wg) primary air pressure at the nozzles. The replacement Dadanco units require 200Pa, a reduction of 180Pa. The original and design total pressure at the primary air fan was 1500Pa (6.0”wg). With the Dadanco units the total pressure reduces to 1320Pa. What is the saving in fan power?
 
Answer: From the fan laws, the relationship of the new total pressure to the old is given by:
 
p2 = p1 x (n2 / n1)2 x (d2 / d1)2 x (r1 x r2)1, where
 
p = pressures, 1 original and 2 the revised values for p, n, d and r.
 
n = speed of the fan, r/s
 
d = fan diameter – which does no change and this element can be deleted
 
r = density of the air, which does not change and can also be deleted
 
Then
p2 = p1 x (n2 / n1)2, and p2/p1 is 0.88.
 
As n2 / n1 the square root of p2/p1, the ratio of the speeds is 0.9381.
 
If we now consider the law relating the change in power, PR, it is similar to the pressure change equation, and can be reduced similarly to:
 
PR2 = PR1 x (n2 / n1)3
 
PR2  = PR1 x 0.93813
 
PR2  = 0.8255 PR1
 
This represents a reduction of 17.45% in fan power.
 
The above presentation draws from the well presented Fan Laws page in the Fantech® catalogue.
 
Please note that it was the total fan pressure that was used.
 

What proportion of the load is handled by the primary air and what by the secondary coil?

If you are starting out on a design and need a feel for the division of the load between the primary air and the secondary water, allow for the primary air to handle all of the transmission load, the room latent load and a part of the sensible loads of the space being considered.
 
The load to be handled by the secondary water system is the sum of the people, lights, office equipment and the radiant and transmitted solar load. The first three you will have based on normal design standards or the values in a brief, and the others by reference to solar load tables or your heat load calculation program. The secondary load will vary from one project to another, but as a first approximation, allow for the secondary circuit to handle 60% of the load on a room or zone.
 
Do not include the outdoor air load, as the primary air handler will cope with this. If you use Camel, the program will include a part of the outdoor load equal to the bypass factor component. The “error” resulting from this is small and can be neglected. A word of caution though, don’t let the bypass factor get stuck at 0.15. It will be much smaller for a larger or central plant unit and coil, and possibly lower for a packaged fan-coil unit. Check it out.
 

How many units can be controlled from one control valve?
Depending on the piping design and layout, it could be one or several. A single temperature sensor can control a zone, and then control one or more automatic control valves, each valve controlling the flow to one or more induction terminal units. The piping and valves after the control valve should be such that the water flow to each unit is at the required design flow. It is not out of the question for each unit to have its own control valve, if the zoning or office requirements want this.
 
It is not unusual for a pair of units on the perimeter next to one another to have a single control valve. They may even have their primary air supply from a single duct take-off.

 
How low can the secondary chilled water (SCHW) temperature be without causing condensation?
A basis for deciding on a secondary chilled water temperature is to relate it to the room dew point temperature. In theory, a surface at room dew point temperature has the potential to condense water vapour from the air. In still air conditions the air film on this surface will act as a layer of insulation, and allow the temperature of the surface to drop below the room dew point before condensation commences. The effectiveness of the air film depends on the velocity of the air over it. In still air conditions, the air film has the greatest insulating effect and could “increase” the surface to dew point temperature gap by around 1.5K. Therefore for a room dew point temperature of 13oC, a minimum secondary water temperature would be 11.5oC.